The City of Milwaukie and TriMet are partnering to rebuild the Jackson Street
streetscape from 21st to Main Street and add new, high-quality shelters and
other amenities, to improve the area for transit users and the general public.
The project, in combination with future TriMet service changes to reduce
layovers and add new bus stops at Washington Ave., fulfills the highest priority
transit project identified in the
City’s Transportation System Plan.
The City and TriMet contributed funds to engineering; the majority of project
costs will be paid by federal ARRA/“stimulus” funds and Federal Transit
Administration grant funds. The federal ARRA/”stimulus” funds are Federal
Highway Administration (FHWA) monies, allocated regionally, and administered by
the Oregon Department of Transportation (ODOT). Total project cost, including
new shelters, is approximately $1.3 million. The City’s share is expected to be
less than $40,000.
Harper Houf Peterson Righellis is providing design engineering and construction
engineering services on the project. Civil Works NW was the low bidder for civil
construction and will be brought under contract in April. TriMet has contracted
with Trueform to fabricate the new bus shelters.
The streetscape elements were designed in accordance with the guidelines of the
City’s Public Area Requirements. The shelter selection process was informed by
several discussions with the City’s Design & Landmarks Committee (DLC) and a
public open house that addressed all project elements in June 2009.
The Jackson Street Improvement Project includes the following elements:
Full reconstruction of Jackson Street and associated streetscape
(i.e., sidewalks, etc.) between Main and 21st Avenue.
Relocating utilities under-ground. (The picture here illustrates the
visual impact of the existing above-ground utilities.)
New bus shelters, consolidating the existing scattered grouping of
bus shelters along Jackson and 21st Avenue to two high-quality shelters
on Jackson. (The picture below shows the larger shelter, which will be
on the north side of Jackson Street just off Main Street.)
Street furniture, street trees, trash cans, pedestrian-scale
lighting, and City medallions, in conformance with the streetscape
design specified in the Public Area Requirements element of the Downtown
and Riverfront Land Use Framework.
Civil construction is expected to start in May or June, and will
be coordinated with construction of the Jackson Street sculpture garden.
Construction will run through the summer, during which time Jackson Street will
be closed, and TriMet buses will be re-routed. Once the civil construction stage
is complete, TriMet’s contractor will install the new bus shelters.
In order to avoid disturbing any migratory birds that might nest
this spring, the City chose to remove the existing tree tops in February. The
project will plant nine new street trees: a Red Sunset maple and eight Skyline
Honey-locusts. These trees are more appropriate for the location. The oak trees
that were removed had been damaged by pruning and were starting to lift
sidewalks. (See picture below.) In addition, seven “accent” trees will be
planted, including five Dogwoods and two Pacific Crabapples.
For general information on the project, contact: Alex Campbell, Resource and
Economic Development Specialist for the City, at (503) 786-7608 or campbella@ci.milwaukie.or.us.
For questions specifically related to TriMet, please contact Young Park, Project
Manager, at ParkY@trimet.org or (503)
962-2138.